31st July 2006 was our first day in our fantastic new premises. Over 240,000 sq. ft. of floor area providing a warehouse capacity to store all of our stock under one roof, along with state of the art on site testing laboratory and brand new showroom.

Our new contact details are:

Bristan Group Ltd
Birch Coppice Business Park
Dordon
Tamworth
Staffordshire
B78 1SG

Email: enquire@bristan.com
Sales: 0870 4425555
General Enquiries: 0870 4425556
Freefax Orders: 0808 1611002


The new Bristan Headquarters (artists impression).

As Bristan is putting down new foundations for company growth through its sales and product development activity, the physical foundations of Bristan's future growth are already going in.

To facilitate growth in the company the long-awaited, new Bristan Group Headquarters in Tamworth is now well underway. The building will incorporate a 220,000 sq ft warehouse and administration site. Thanks to frenetic activity on the early stages of the building work the project is currently well on schedule for completion in August 2006.

The site has been a hive of activity since the heavy machinery moved in and groundwork on the project began earlier this month. Already drains and foundations pads are in for most of the building and the all the foundation bases which are to receive main steelwork have now been cast. A main access road has been created for site traffic and a platform for scissor lifts has been created which will be utilised for the building cladding.

May 2006 - A view of the office elevation and car parking area.
May 2006 - A view of the reception area from the position of the proposed reception desk. May 2006 - A view of the mezzanine area showing the Cardex small parts retrieval system.
May 2006 - A view of the first-floor office area taken from the southern end showing the managers offices in partitions on the right-hand side. May 2006 - The reception area looking towards the proposed reception desk position.
April 2006 - Conveyors on the mezzanine.
April 2006 - Offices and car park frontage. April 2006 - Toilets in the office areas.
April 2006 - A view over the warehouse showing conveyors being assembled on the mezzanine deck. April 2006 - Views of the first floor office areas.
April 2006 - The main site entrance from the roundabout.
April 2006 - Conveyor parts stored in the central area of the warehouse with the mezzanine in the background.
March 2006 - The hand-railing to the office block staircases being erected.
March 2006 - The new reception area. March 2006 - Office partitioning on the ground floor in the area to the north of reception.
March 2006 - The canteen and kitchen area. March 2006 - A view of the car park from the first floor office window.
March 2006 - The ground floor office area with partly laid carpet tiling. March 2006 - A view across the warehouse showing the narrow aisle racking in the foreground and the mezzanine in the background.
March 2006 - Paving and planting areas at the customer entrance to the trade counter.
March 2006 - Erection of the warehouse racking begins. The mezzanine racking in the foreground and the narrow aisle racks are being started in the background corner of the warehouse from the offices.
March 2006 - The reception area and main entrance draught lobby showing a partly completed ceiling. March 2006 - A general view of what will become the car parking area. The permanent car park is in the background and the area in the foreground will become the overflow parking area which will be grassed.
February 2006 - View from the estate road showing the offices at the south west corner of the site. February 2006 - A view from the warehouse showing the separating firewall between the warehouse and the offices.  Painting and encasement of the steelwork is only partly completed.
February 2006 - The main entrance to the reception and office areas showing the partly completed paving and planting area viewed from the car park. February 2006 - A view across the yard area with concreting now completed showing the loading doors and dock levellers and the access ramp to the large vehicle access doors at warehouse floor level.
January 2006 - Offices - first floor preparing for the concrete floor sealing and the installation of the raised flooring.  The boxes contain the steel covered particle board floor tiles.  The walls are boarded and plastered, as are the column casings and the ceiling mounted services are installed. January 2006 - General view of warehouse interior from the area of the at-grade loading doors looking to the rear (north) wall.  Order will come from chaos.
January 2006 - SW corner of the offices showing the cladding and windows approaching completion. January 2006 - Looking west along the front yard area showing the loading docks with dock levellers and preparations for slab concreting. The blockwork in the foreground is the retaining wall at the east end of the yard under construction.
January 2006 - View from the office area at second floor level overlooking the warehouse showing the recently completed floor slabs. January 2006 - A view of the loading docks and dock levellers with recently cast yard slabs in the foreground.
January 2006 - The ground floor area of the offices looking towards the reception area, showing progress on wallboarding and plastering as well as the extent of the ceiling mounted services.
December 2005 - West elevation of warehouse and offices. November 2005 - This is looking on to the SW/E elevations - the offices elevations are progressing with the blockwork piers and when complete the cladding and windows will commence.
November 2005 - Offices ground floor mechanical 1st fix installations in the ceiling service void area. November 2005 - The offices elevations are ongoing with the blockwork piers and when complete the cladding and windows will commence.
November 2005 - Looking at high level in to the warehouse - you can see that the sub-grid is in place to the warehouse ceiling ready for sheeting. November 2005 - SE elevation of the warehouse showing the loading doors and dock levellers.
November 2005 - This is looking on to the SW/E elevations - the offices elevations are ongoing with the blockwork piers and when complete the cladding and windows will commence.
October 2005 - Ground floor office area with floor and internal walls completed. Staircase leads to the first floor. October 2005 - The concrete floor is laid to the ground floor offices.
October 2005 - The roof panels are being installed. October 2005 - View Showing the new service yard which will house 12 docking bays.
October 2005 - Work continues on the offices, showing stairs to the first and second floors. October 2005 - The steelwork is almost complete.
October 2005 - Bristan's CEO, Steve Lee and MD Roger Williams don their hard hats to check progress on site.
September 2005 - Reinforced concrete bases are laid. September 2005 - Steelwork has been erected for the full length of one of the gridlines. Rafters have already been added for the full width of what will become the warehouse.
August 2005 - The brown field site is cleared in preparation. August 2005 - The digging of foundations to support Bristan's new Group Headquarters are underway.